The works are complete, and the site has been provisionally handed over. Months later, the contractor is still waiting for the return of its performance security and payment of retained amounts. The delay may begin with one unresolved item in the handover record: “repair paintwork.” Without an exact location or documented closure, even a minor defect can become a disputed obligation. Whether it justifies withholding either amount, however, depends on the contract and applicable law.
This guide explains provisional and final handover under Syria’s Law No. 51 of 2004 and the corresponding procedures under FIDIC 2017. It distinguishes performance security from retention money, explains what may be released at each stage, and shows how to document outstanding defects so that their closure can be verified.
Construction handover stages and retention release conditions
Under Syria’s Law No. 51 of 2004, public works contracts provide for provisional and final handover. The contract’s special conditions determine the obligations associated with each stage, including the applicable defects liability period. Separate statutory liabilities may continue after final handover.
The table distinguishes the return of final securities from the release of retention money deducted from the contractor’s payments.
| Stage | What happens | What is released |
|---|---|---|
| Provisional handover | The public body’s committee inspects the works and records outstanding defects or obligations in accordance with the contract. | Final securities are returned under Article 47 unless outstanding contractor obligations justify withholding them. Retention money follows separate contractual provisions. |
| Defects liability period | The contractor remedies notified defects and documents their closure within the agreed period. | No automatic release follows merely from the passage of time. Any retention release depends on the contract’s conditions. |
| Final handover | The committee verifies that the requirements for final acceptance have been satisfied. | Any remaining retention and final settlement are handled under the applicable contractual and payment provisions. Article 61 does not itself establish a general payment-release date. |
Ten-year liability is not a fourth handover stage. Under Article 617 of the Syrian Civil Code, qualifying structural collapse or serious defects threatening a building’s stability and safety may give rise to liability within ten years of handover. This liability is separate from contractual retention and performance security.
Provisional and final handover under Syrian Law No. 51
Construction contracts may use terms such as initial acceptance, provisional handover, practical completion, or taking-over. These describe related milestones, but their legal and financial consequences are not necessarily identical.
Article 61 of Law No. 51 of 2004 requires public bodies to appoint committees to receive works, supplies, or services. The general conditions govern how these committees operate, while the special conditions establish the conformity guarantees and the parties’ rights and obligations at provisional and final handover.
For contractors, the practical implication is straightforward: the handover certificate alone does not establish when every retained amount becomes payable. Check the special conditions for the defects period, acceptance requirements, outstanding obligations, and payment-release procedures.
The same distinction matters when comparing Syrian public works contracts with FIDIC-based agreements. A FIDIC Taking-Over Certificate and Performance Certificate serve related purposes, but their effects must be assessed under the signed contract, its Particular Conditions, and applicable law.
Before relying on Law 51 for a particular project, confirm the applicable version of the legislation, including subsequent amendments, and the conditions governing that contract.
Why retention release can stall after completion
Completion of the works does not necessarily complete the financial closeout. A contractor may have finished the defects period but still lack signed evidence that individual snags were closed, approved test records, or contractually required as-built drawings.
These gaps can delay acceptance procedures or payment certification. However, a delayed retention payment and an unreleased performance security are separate issues: the party withholding either must have a legal or contractual basis for doing so.
For each outstanding item, the contractor should identify the relevant contract requirement, the evidence needed to demonstrate compliance, and the person authorized to confirm closure.
The financial consequences can continue while the issue remains unresolved. Where a bank charges periodic guarantee commissions, an extended security validity period adds cost. Unpaid retention also reduces working capital available for subsequent projects.
The following sections explain how release conditions differ under Syrian public works contracts and FIDIC 2017, and which documentation practices can reduce avoidable handover delays.
Also read: Construction Companies in Syria 2026: How to Compare and Choose

Defects liability period and construction retention release
The defects liability period determines how long the contractor must address defects covered by the contract after handover. Its expiry can trigger the release of remaining retention money, but it does not automatically settle every outstanding payment or release every performance guarantee.
For Syrian public works contracts, Article 61 of Law No. 51 of 2004 does not prescribe a uniform defects liability period. The applicable duration and handover obligations must be established from the contract and its special conditions.
Return of final securities Under Syrian Law No. 51
Article 46 of Law No. 51 of 2004 sets final securities at 10% of the contract value as the general rule, subject to the reductions and exemptions permitted by the law.
Article 47 establishes different release conditions according to the contract type:
- Works contracts: Final securities are returned in full after provisional handover, provided the contractor has no outstanding obligations that justify withholding them.
- Supply and service contracts: Final securities are returned after final handover.
For a public works contractor, the provisional handover record is therefore a key document for recovering final securities. However, signing the record does not necessarily resolve outstanding contractual liabilities or establish entitlement to all remaining payments.
Final securities are not the same as retention money. Amounts withheld from interim payments require a separate examination of the contract’s payment and release provisions. Article 47 should not be interpreted as automatically governing those deductions.
Before requesting release, verify the provisional handover record, any outstanding obligations identified by the public body, and the applicable contractual provisions.
FIDIC 2017 handover certificates and retention release
The FIDIC 2017 Red Book distinguishes taking-over, completion of outstanding obligations, retention release, and return of performance security.
Under Sub-Clause 10.1, the contractor may apply for a Taking-Over Certificate by giving Notice no earlier than 14 days before the expected completion date. The Engineer then has 28 days to issue the certificate or reject the application with reasons.
Minor outstanding work or defects that do not substantially affect safe use for the intended purpose may be listed in the certificate. If the Engineer fails to respond, the certificate may be deemed issued where the contractual conditions are satisfied.
Retention money is released in two stages under Sub-Clause 14.9:
- First half: After the Taking-Over Certificate is issued, the contractor includes the first half of the retention money in a payment Statement.
- Second half: After the latest applicable Defects Notification Period expires, the contractor includes the remaining half in a Statement.
The Engineer certifies the applicable release in the next Interim Payment Certificate after receiving the Statement. If work remains outstanding under Clause 11, the Engineer may withhold certification of its estimated cost until that work is completed.
Performance security follows a different procedure. Under Sub-Clause 11.9, the Engineer issues the Performance Certificate after the relevant defects notification periods and completion of the required documents, testing, and remedial work, subject to the clause’s timing requirements.
Under Sub-Clause 4.2.3, the Employer must return the Performance Security within 21 days after the Performance Certificate has been issued and the contractor has fulfilled the site clearance requirements under Sub-Clause 11.11.
The Syrian and FIDIC procedures have comparable functions, but their certificates and administrative authorities are not legally interchangeable.
| Syrian public works contracts | FIDIC 2017 Red Book |
|---|---|
| Provisional handover | Taking-Over Certificate under Sub-Clause 10.1 |
| Contractual defects liability period | Defects Notification Period under Clause 11 |
| Final handover | Performance Certificate under Sub-Clause 11.9 |
| Handover committee appointed by the public body | Engineer administering the relevant FIDIC certification procedures |
These are functional comparisons rather than direct legal equivalents. The contract’s Particular Conditions and governing law determine which procedures apply and whether standard FIDIC provisions have been amended.
Ten-year construction liability under the Syrian civil code
Final handover and the return of performance security do not automatically end the contractor’s statutory liability for serious structural defects.
Under Article 617 of the Syrian Civil Code, the architect and contractor may be jointly liable for total or partial collapse of buildings or other fixed structures. The provision also covers defects that threaten the structure’s stability and safety, even where no collapse has occurred.
The ten-year period begins when the works are received, subject to the scope and exceptions established by the law.
Article 618 limits an architect’s liability to design-related defects when the architect was responsible for preparing the design but not supervising construction.
This statutory liability is separate from the contractual defects period. Contractors should therefore retain relevant design approvals, inspection records, test results, and handover documents after final acceptance, particularly where structural responsibility may later be disputed.

How to prepare for final handover in construction
Delays in final handover can arise when completed repairs cannot be verified or required project documents remain unapproved. A properly maintained handover record helps establish which obligations have been completed and which remain outstanding.
However, closing these items does not automatically release retention money or performance security. The applicable contract determines the requirements for acceptance, certification, and payment.
How to document and close construction snags
A snag recorded simply as “repair paintwork” is difficult to close because it does not identify the affected area, the required repair, or how completion will be verified.
Compare the following entries:
- Vague snag: Repair paintwork.
- Verifiable snag: Floor 3, Flat 7, north living-room wall — approximately 1 m of hairline cracking in the paint finish. Investigate the cause, repair the affected area to the approved finish specification, and submit the completed work for inspection by the authorised representative.
The revised entry identifies the location, defect, corrective action, and acceptance requirement. It allows the contractor and inspecting party to verify the same item against an agreed standard.
A construction snag list should also record responsibility, deadlines, supporting evidence, and formal closure:
| ID | Location and defect | Required action | Due date | Status and evidence | Closure verification |
|---|---|---|---|---|---|
| 14 | Floor 3, Flat 7, north wall — hairline cracks in paint finish | Investigate and repair to approved specification | Agreed deadline | Repair completed; inspection pending | Authorised signatory and date to be recorded after acceptance |
For each item, retain the original inspection reference and supporting evidence, such as photographs or test results where relevant. Record the closure date only after the person authorised under the contract has verified the corrective work.
This creates a traceable record of completed obligations. Whether an unresolved item affects final acceptance or retention release must still be determined under the contract.
Six documentation mistakes that delay final handover
Even when construction work is substantially complete, missing records and unresolved approvals can delay the handover process. Six issues deserve particular attention:
- Untraceable snag items. Descriptions such as “repair finishes” leave the scope open to interpretation. Record the exact location, defect, corrective action, responsible party, and evidence required for closure.
- An unclear defects period start date. Without an identifiable contractual commencement date, the parties may disagree over when the period ends. Retain the signed handover record or relevant certificate and verify the commencement date under the contract.
- Late handover applications. Completing the works does not replace a required formal notice or application. Submit the request through the prescribed procedure, observe contractual notice periods, and retain proof of receipt.
- Incomplete as-built drawings. Drawings that do not reflect executed changes may be rejected during review. Update them throughout construction and maintain revision records showing which drawings have been submitted and approved.
- Missing test and commissioning records. Completed tests may still require documented results and acceptance. File the required reports as testing progresses, with the signatures or approvals specified in the contract.
- Incomplete warranties and O&M documentation. Equipment warranties, operating instructions, and maintenance manuals should be tracked against contractual deliverables. Collect them from suppliers and subcontractors before the final submission deadline.
Before requesting final handover, reconcile the outstanding-items register with the contract’s acceptance requirements. Identify every incomplete item, its responsible party, the evidence still required, and the authority responsible for approval.
If acceptance or payment remains disputed, preserve the notices, inspection records, and correspondence needed to establish the contractual position. Any dispute should follow the resolution procedure specified in the contract.
Read more: Infrastructure Contracting in Syria: Choosing the Right Contractor

13 checks before final handover in construction projects
Before submitting a final handover request, verify that the outstanding work, required documents, and payment records are consistent with the contract’s acceptance conditions.
Use this checklist to identify gaps that could delay handover or the release of outstanding payments and securities.
- Verify provisional handover records. Confirm the acceptance date, required signatures, and any outstanding obligations recorded at provisional handover.
- Confirm the defects period expiry date. Calculate the applicable end date under the contract, including any valid extensions or separate periods for project sections.
- Close outstanding snags. Check that each item has been completed, inspected, and supported by dated closure evidence approved by the authorised representative.
- Complete test and commissioning records. Verify that all contractually required tests are documented, with results and approvals organised in a traceable register.
- Obtain acceptance of as-built drawings. Confirm that the drawings reflect the executed works and have been submitted, reviewed, and accepted in the required formats.
- Complete O&M documentation. Provide operation and maintenance manuals for the relevant equipment and systems, with evidence of submission and acceptance.
- Verify manufacturer warranties. Confirm the warranty scope, commencement date, beneficiary, and supporting certificates required by the contract.
- Review performance security requirements. Check the guarantee’s validity, expiry, and contractual release conditions. Arrange an extension only where required under the applicable obligations.
- Reconcile retention money. Compare amounts deducted, previously released, and still held against approved payment certificates. Identify which amounts have become due under the contract.
- Reconcile quantities and the final account. Verify approved measurements, variations, and payment adjustments. Record unresolved differences and preserve the supporting documentation rather than assuming they must all be settled before handover.
- Document defects reported during the defects period. Confirm that each notification, corrective action, inspection result, and closure decision is recorded separately from the original handover snag list.
- Submit the final handover request correctly. Follow the contract’s notice procedure, identify the required supporting documents, and retain proof of submission and receipt.
- Check the contract’s special conditions. Verify any project-specific acceptance criteria, additional deliverables, approval authorities, notice periods, and conditions affecting final certification or payment.
Completing these checks helps establish that the project is ready for final acceptance. The release of retention money, return of performance security, and settlement of outstanding payments must still follow their respective contractual procedures.
For water networks, treatment facilities, and other relevant EPC infrastructure projects, contact Qiwaa Advance with your project scope, technical specifications, and testing and handover requirements to discuss the contracting services available through Qiwaa Contracting.

EPC water infrastructure handover with Qiwaa Advance
Qiwaa Contracting, the contracting division of Qiwaa Advance, undertakes Engineering, Procurement, and Construction (EPC) projects in Syria, including water networks, desalination facilities, and wastewater treatment plants.
Handover requirements for these projects extend beyond completing physical construction. Depending on the contract, acceptance may require pipeline testing, equipment commissioning, approved as-built drawings, material conformity records, and operation and maintenance documentation.
Through our relationship with Amiantit, Qiwaa Advance supports the procurement and technical coordination of GRP pipe systems for water infrastructure projects. Relevant documentation can include:
- GRP pipe systems: Manufacturer conformity certificates, approved specifications, pipe identification records, and applicable inspection and test reports.
- HDPE pipe systems: Where included in the approved project supply scope, material certificates, installation and jointing records, and relevant testing documentation.
These records help demonstrate that supplied and installed materials meet the approved project requirements. The exact documents and acceptance criteria must be established by the contract.
A complete handover file supports acceptance and certification procedures. However, the return of performance security and release of retention money remain subject to the applicable contractual provisions.
Why early handover documentation matters in EPC projects
Preparing the handover file during construction allows contractors to identify missing records while the relevant work, personnel, and inspection evidence are still available.
The table compares the practical implications of preparing records progressively with compiling them at the final handover stage.
| Document | Prepared During Construction | Compiled at Final Handover |
|---|---|---|
| Test records | Results and approvals are recorded after each required test. | Missing records may require additional verification or repeated testing. |
| As-built drawings | Changes are recorded as work progresses and submitted for review. | Installed details must be reconstructed from site records. |
| Snag closure records | Corrective actions and acceptance evidence are tracked in one register. | Contractors may need to reconcile separate reports and correspondence. |
| Material certificates | Delivery records and product identification remain traceable to approved specifications. | Missing certificates or identification records may delay verification. |
| Manufacturer warranties | Required documentation is collected and checked during procurement. | Missing warranties must be obtained from suppliers before acceptance. |
| Handover readiness | Outstanding documents can be identified before the final submission. | Documentation gaps may become apparent only during the final review. |
Progressive documentation requires coordination throughout construction, but it reduces the risk of discovering missing evidence at handover.
How to organize handover documents for water infrastructure projects
For an EPC water network or treatment facility, the handover document register should be developed from the contract scope, technical specifications, approved drawings, and inspection and test requirements before construction begins.
Each required deliverable should identify its responsible party, submission deadline, approval authority, and current status.
For water infrastructure projects, the register may cover:
- Pipeline inspection and testing: Required pressure or leakage tests, inspection reports, and acceptance records.
- Material traceability: Approved pipe specifications, manufacturer certificates, and delivery or identification records.
- Treatment equipment commissioning: Applicable equipment tests, functional checks, and commissioning reports.
- As-built documentation: Final pipeline routes, installed equipment details, and approved design changes.
- Operation and maintenance records: Equipment manuals, warranties, and any required operator training documentation.
- Outstanding work: Snag lists, corrective actions, inspection evidence, and authorised closure records.
The contractor should confirm which tests require witnessing, the required document formats, and the applicable submission and approval procedures with the responsible parties under the contract.
Updating the register throughout procurement, installation, testing, and commissioning makes outstanding documentation easier to identify before final acceptance.
Contact Qiwaa Advance to discuss EPC execution and infrastructure supply requirements for your water network or treatment project in Syria. Provide the project scope, technical specifications, and testing requirements so the team can assess the relevant contracting and supply services.
Read more: Water Desalination Plants in Syria by EPC Model

FAQs about final handover of a construction project
When Is retention money released under FIDIC 2017?
Under Sub-Clause 14.9 of the FIDIC 2017 Red Book, the contractor can claim the first half of the retention money after the Taking-Over Certificate is issued. The second half becomes eligible for release after the latest applicable Defects Notification Period expires. Both amounts must follow the contractual statement and payment certification procedures. The Engineer may withhold certification of the estimated cost of outstanding work under Clause 11.
When are final securities returned under Syrian public works contracts?
Under Article 47 of Syria’s Law No. 51 of 2004, final securities for public works contracts are returned after provisional handover unless outstanding contractor obligations justify withholding them. For supply and service contracts, they are returned after final handover. These securities are distinct from retention money deducted from interim payments, which follows the applicable contractual provisions.
When Is performance security returned under FIDIC 2017?
Under Sub-Clause 4.2.3 of the FIDIC 2017 Red Book, the Employer must return the Performance Security within 21 days after the Performance Certificate is issued and the contractor has fulfilled the site clearance obligations under Sub-Clause 11.11. The signed contract and its Particular Conditions must be checked for amendments to these requirements.
How long is the defects liability period in Syrian construction contracts?
There is no single duration established by Article 61 of Law No. 51 of 2004 for all public works contracts. The applicable period must be determined from the contract and its special conditions. Contractors should verify its commencement date, expiry date, and any valid extensions before scheduling final handover or claiming payments linked to its expiry.
Can unresolved snags delay final handover or retention release?
Yes, where the outstanding work affects contractual acceptance or release conditions. An unresolved snag may delay handover certification or justify withholding an amount permitted by the contract. Contractors should document each defect’s location, required corrective action, inspection evidence, and authorised closure. Not every minor snag automatically justifies withholding all retention money or performance security.
What documents are required before final handover?
Requirements vary by contract, but commonly include signed provisional handover records, closed snag lists, approved as-built drawings, test and commissioning reports, O&M manuals, and applicable manufacturer warranties. Contractors should also reconcile payment certificates and retention records, verify notice requirements, and obtain the approvals specified in the contract before submitting the final handover request.
Sources
- Law No. 51 of 2004, Contracts System for Public Bodies, Aleppo City Council data bank, 9 December 2004
- Engineers’ liabilities under the Civil Code (Articles 617 and 618 of the Syrian Civil Code, in Arabic), Mohamah.net, undated
- Construction Contract 2nd Ed (2017 Red Book), FIDIC, reprinted November 2022
- Taking over: the meaning of completion under the 2017 FIDIC Contracts, Fenwick Elliott, 8 August 2019