FIDIC contracts in Syria must be assessed against the applicable Syrian legal framework, not just the chosen FIDIC book. Before signing, contractors and developers need to establish who bears quantity overruns, design errors and variation costs—and how those risks affect payment and claims.
This guide compares contract structures, FIDIC risk allocation and the legal provisions that can affect those responsibilities.
Which laws apply to FIDIC contracts in Syria?
FIDIC forms are not a separate Syrian statutory contract regime. Their provisions apply when incorporated into an agreement, subject to the governing law and mandatory legal requirements.
For public construction contracts, the relevant framework includes Law No. 51 of 2004 and, where applicable, the General Conditions issued under Decree No. 450 of 2004. Private construction contracts are governed by the Syrian Civil Code and the parties’ agreed terms, subject to mandatory rules.
Public vs private construction contracts in Syria
| Issue | Public construction contract | Private construction contract |
|---|---|---|
| Legal framework | Law 51, applicable General Conditions and special contract conditions | Civil Code, agreed contract terms and applicable mandatory rules |
| Use of FIDIC | Contract provisions must be compatible with the applicable public procurement framework | Parties may adopt a FIDIC form, subject to mandatory law |
| Quantity and payment risk | Depends on the tender conditions, pricing structure and applicable legal provisions, including Article 8 of Law 51 | Depends on the agreed pricing structure and contract, including Civil Code Articles 623–624 where applicable |
| Dispute resolution | Administrative courts, with arbitration permitted under the conditions of Article 66 of Law 51 | Competent courts or a validly agreed arbitration procedure |
Decennial liability is a separate legal consideration. Under Article 617 of the Civil Code, architects and contractors may be jointly liable for qualifying structural collapse or serious defects affecting buildings and other permanent structures within ten years of handover. Article 618 limits the liability of an architect engaged only for design to defects arising from that design.
Article 619 makes contractual clauses intended to exclude or limit this statutory guarantee void. The application of these provisions must be assessed against the parties’ roles and the particular works.
For contractors, the key distinction is that adopting a FIDIC form does not remove applicable statutory obligations. The signed contract, its particular conditions and the governing law must be reviewed together.
Contract clauses that shift quantity and design risk
The most significant pricing risks often arise from clauses that transfer responsibilities without clearly defining their limits.
Three issues deserve attention before signing:
- Quantity risk: Does the BOQ determine payment through remeasurement, or does the contractor accept a fixed price for the defined scope? Identify who bears quantity discrepancies and when changes qualify for additional payment.
- Design responsibility: Does the contractor design the works, verify employer-provided information or guarantee specified performance outcomes? Check how errors, incomplete drawings and changes to the employer’s requirements are treated.
- Claim deadlines: Which contract edition and particular conditions govern notices for variations, additional payment and extensions of time? Identify deadlines and documentation requirements before work starts.
The contract’s pricing structure, design responsibilities and claims procedures must be consistent with the risks included in the bid.
Before signing a FIDIC-based construction contract in Syria, contractors should identify each transferred risk, its contractual limits and the mechanism for recovering additional time or payment when the contract permits it.
Read more: Construction Companies in Syria 2026: How to Compare and Choose

Construction contract types in Syria and risk allocation
Before selecting a construction contract, distinguish between how the contractor is paid and who is responsible for design and delivery. Lump sum, unit rate and cost plus define pricing arrangements. Design-build and EPC define how project responsibilities are allocated and can use different payment structures.
| Pricing arrangement | How payment works | Quantity and cost exposure | What to verify |
|---|---|---|---|
| Lump sum | Agreed price for a defined scope, paid according to the contract | Contractor generally bears the cost of quantities needed to complete the agreed scope, subject to contractual adjustments | Scope boundaries, BOQ status, design changes and variation rights |
| Unit rate | Agreed rates applied to measured, payable quantities | Employer generally bears changes in payable quantities; contractor remains exposed to the adequacy of its rates | Measurement rules, quantity changes and rate-adjustment provisions |
| Cost plus fee | Reimbursement of allowable documented costs plus an agreed fee | Employer generally bears more cost uncertainty, subject to exclusions, controls and contractual limits | Allowable costs, fee calculation, audit rights and any cost ceiling |
Design responsibility must be assessed separately. A lump-sum contractor does not automatically assume all design liability, and a unit-rate contractor is not automatically protected from design obligations.
Lump sum vs unit rate contracts when quantities change
Consider a hypothetical excavation item priced at USD 10 per m³, with an estimated quantity of 1,000 m³. The initial value is USD 10,000, but the completed work measures 1,200 m³.
If the additional 200 m³ is required to complete the original scope, with no instructed variation:
- Lump sum: The agreed USD 10,000 may remain unchanged where the contractor bears the quantity-estimation risk. Additional payment depends on the contract and applicable law.
- Unit rate: If all 1,200 m³ are measured and payable at the agreed rate, the amount becomes USD 12,000. The contract may provide for rate adjustments in specified circumstances.
The result changes if the employer instructs additional work or modifies the design. Such changes must be assessed under the contract’s variation and valuation provisions rather than treated automatically as quantity overruns.
For Syrian public contracts, Article 62 of Law No. 51 of 2004 permits the authorised official to increase or decrease contracted quantities during execution by up to 30% per item, provided the total value of the increase or decrease does not exceed 25% of the contract value. Within those limits, the law provides for the existing contractual prices and conditions and additional time proportionate to increased work.
A 20% increase in one item is within the individual-item limit, but the overall contract-value limit must also be satisfied. Contractors must distinguish an authorised quantity adjustment from a measurement discrepancy before assuming entitlement to additional payment.
EPC design responsibility and cost-plus pricing
EPC and cost plus are not alternative contract types at the same level. EPC allocates responsibility for engineering, procurement and construction; cost plus determines how the contractor is compensated.
Under an EPC arrangement, one contractor generally assumes responsibility for delivering the defined project scope, including the design obligations allocated to it. The contract commonly uses a lump-sum price, although EPC does not by itself establish every payment or risk provision.
For water networks, pumping stations and treatment plants, contractors should verify who is responsible for:
- Design development and errors in employer-provided information.
- Equipment selection, procurement and technical interfaces.
- Site investigations, unforeseen conditions and utility connections.
- Testing, commissioning and specified performance requirements.
A cost-plus arrangement may be considered where the scope or existing conditions cannot be reliably defined before work starts, such as certain emergency repairs or rehabilitation projects.
However, reimbursable payment requires clear rules for allowable costs, supporting records, approvals and audit rights. A fixed fee may reduce incentives linked to increasing reimbursable costs, but neither a fixed nor percentage-based fee removes the need for cost controls.
The practical decision is whether the scope and risks can be defined and priced reliably, and which party is best placed to manage them.
FIDIC red, yellow and silver books for Syrian projects
The FIDIC Red, Yellow and Silver Books provide different starting points for allocating design, payment and construction risks.
| FIDIC contract | Main design responsibility | Typical payment basis | Key risk consideration |
|---|---|---|---|
| Red Book – Construction | Employer-designed works, although specified elements may be designed by the contractor | Remeasurement using contractual rates | Quantity measurement, design changes and valuation of variations |
| Yellow Book – Plant and Design-Build | Contractor designs to the Employer’s Requirements | Generally lump sum, subject to contractual adjustments | Design compliance, performance obligations and claims arising from changed conditions |
| Silver Book – EPC/Turnkey | Contractor assumes extensive design and delivery responsibility | Generally lump sum | Greater transfer of completion, design and site-condition risks to the contractor |
The appropriate form depends on the project’s design maturity, risk profile and the owner’s requirements.
- Red Book: Often appropriate where the employer provides the main design and expects payment based on measured work.
- Yellow Book: Suited to contractor-designed facilities, including plant and infrastructure projects, where contractual mechanisms allocate defined risks between the parties.
- Silver Book: Intended for EPC/turnkey projects seeking greater certainty of price and completion responsibility, provided contractors have adequate information and opportunity to assess the transferred risks.
The Silver Book is not automatically appropriate for every EPC project. FIDIC cautions against its use where tenderers lack sufficient time or information to assess the Employer’s Requirements or where substantial underground work cannot be adequately investigated without special provisions.
This matters for water and sewer networks in Syria, where ground conditions, existing utilities and incomplete site information may materially affect construction costs.
FIDIC’s second editions of the three books were published in 2017 and reprinted with amendments in 2022. Contractors should confirm the edition, applicable amendments and Particular Conditions before relying on the standard allocation of responsibilities.
The selected FIDIC book is only the starting point. The signed agreement, Employer’s Requirements, Particular Conditions and applicable Syrian law determine the obligations that must ultimately be priced and performed.
Also read: Water Desalination Plants in Syria by EPC Model

How to review FIDIC contracts in Syria before signing
Before signing a FIDIC-based construction contract in Syria, contractors should review the allocation of design, quantity and payment risks alongside the applicable legal requirements. The contract’s edition, Particular Conditions and supporting documents determine how these obligations operate.
Prioritise seven checks:
- Contract structure and document priority: Identify the FIDIC edition, project delivery model, pricing arrangement and order of precedence when contractual documents conflict.
- Design and quantity responsibility: Establish who designs each part of the works, verifies employer-provided information and bears quantity discrepancies.
- Measurement and payment: Review payment milestones, measurement rules, certification periods, advances, retention and price-adjustment provisions.
- Variations: Confirm who can instruct changes, how they are valued and when additional time or payment may be claimed.
- Claims and notices: Identify every applicable notice deadline, required supporting records and procedure for contesting a determination.
- Securities and liability: Check performance guarantees, advance guarantees, delay penalties, insurance obligations and liability limitations.
- Dispute resolution: Verify the agreed dispute procedure, competent forum and any mandatory Syrian legal requirements affecting arbitration.
The objective is to identify which risks the contractor must price, which changes may justify additional payment or time, and which notice requirements protect those rights.
Syrian public contracts law and FIDIC clauses
For contracts with Syrian public bodies governed by Law No. 51 of 2004, FIDIC provisions must be reviewed alongside the applicable statutory rules. Particular Conditions cannot simply replace mandatory legal requirements.
The following provisions are especially relevant when reviewing a draft contract:
| Issue | Law 51 provision | What to check in the contract |
|---|---|---|
| Final security | Article 46 generally sets 10% of the contract value, subject to permitted reductions and exemptions | Required amount, accepted instrument, submission deadline and release conditions |
| Advance payment | Article 49 permits an advance of up to 15% when expressly provided for, after the commencement order and against a sufficient bank guarantee | Advance eligibility, guarantee requirements, recovery terms and price-adjustment consequences |
| Delay penalties | Article 50 generally requires at least 0.1% daily, with an aggregate ceiling of 20%, subject to applicable exceptions | Completion dates, penalty calculation, extension procedures and relevant relief provisions |
| Quantity adjustments | Article 62 provides for adjustments within 30% per item and an overall 25% contract-value limit under its conditions | Who authorises changes, applicable rates, quantity records and additional time |
| Contract documents | Article 68 establishes an order of precedence for conflicting contract documents | Consistency between the agreement, special conditions, general conditions, drawings, specifications and price schedules |
| Instructions and claims | Article 69 provides 15-day deadlines for specified objections, reservations and claims | Notice triggers, written instructions, authorised recipients and proof of delivery |
| Arbitration | Article 66 establishes administrative-court jurisdiction and permits arbitration subject to prescribed conditions, including special provisions for external contracts | Whether the proposed arbitration mechanism and forum are legally permissible |
The contractual documentation also matters. Under Article 68, the agreement takes precedence over the special conditions, followed by the general conditions, technical specifications and drawings, price schedules, and accepted contractor offer, within the applicable legal framework.
For contractors, this means that an obligation stated in a drawing, BOQ note or Particular Condition must be considered together with the contractual document hierarchy and mandatory law.
Special attention is required for claims under Article 69. A contractor receiving an instruction that exceeds its contractual obligations, or encountering certain unforeseen circumstances, may face a 15-day deadline to preserve objections or claims. FIDIC notice periods should not be treated as substitutes for these statutory requirements without legal review.
Likewise, incorporating FIDIC’s dispute procedures does not automatically make its standard arbitration provisions enforceable against a Syrian public body. Article 66 requires a contract-specific assessment.
Decennial liability under Civil Code Articles 617–619 also remains relevant where applicable, including the prohibition on clauses excluding or limiting that statutory guarantee.
FIDIC 2017 claim deadlines for red, yellow and silver books
The 2017 second editions of the FIDIC Red, Yellow and Silver Books provide structured procedures for claims and dispute resolution.
For claims seeking additional payment or extensions of time, the standard sequence generally includes:
- 28 days for a Notice of Claim. Under Sub-Clause 20.2.1, the claiming party generally gives notice within 28 days after it became, or should have become, aware of the event or circumstance.
- 84 days for a fully detailed claim. Under Sub-Clause 20.2.4, the claimant generally submits the contractual or legal basis, contemporary records and supporting particulars within 84 days of that same awareness date—not 84 days after the initial notice.
- 42 days for consultation and agreement. Following the relevant submission or referral, the Engineer or Employer’s Representative generally has 42 days to seek agreement, subject to the contractual procedure.
- A further 42 days for determination. If agreement is not reached, the responsible contract administrator generally has another 42 days to issue a determination.
- 28 days for a Notice of Dissatisfaction. A party dissatisfied with the determination generally must issue its notice within 28 days.
- 42 days to refer the dispute to the DAAB. Where the dispute follows a determination and Notice of Dissatisfaction, the standard procedure generally requires referral within 42 days of the notice.
- 84 days for the DAAB decision. The Dispute Avoidance/Adjudication Board generally issues its decision within 84 days of receiving the referral, unless another period is agreed or an applicable exception operates.
A party dissatisfied with the DAAB’s decision generally has a further 28 days to issue a Notice of Dissatisfaction, under Sub-Clause 21.4.4.
The main administrative distinction is that the Red and Yellow Books use the Engineer for agreement and determination under Sub-Clause 3.7, while the Silver Book uses the Employer’s Representative under Sub-Clause 3.5.
Missing a deadline can affect entitlement, but the 2017 forms also contain procedures concerning late notices, responses and justification for delays. The consequences depend on the relevant clause, the parties’ actions and the governing law.
These time periods describe the standard 2017 framework. Contractors must check the applicable FIDIC edition and amendments, the Particular Conditions and any overriding legal requirements.
For Syrian public contracts, review FIDIC’s claims timetable alongside Article 69 of Law 51. Where different notice requirements may apply to the same event, establish the legally effective procedure before execution begins rather than attempting to resolve the conflict after a claim arises.

12 checks before signing FIDIC contracts in Syria
Before signing a FIDIC-based construction contract in Syria, identify the clause governing each risk and record any unresolved responsibilities or conflicting provisions.
- Contract documents: Which FIDIC edition and Particular Conditions apply, and which document takes precedence if the agreement, drawings and BOQ conflict?
- Design responsibility: Who prepares and verifies the design, and who bears errors in employer-provided information or unforeseen site conditions?
- Quantity risk: Is payment lump sum or remeasured, and who bears BOQ quantity discrepancies?
- Payment terms: How are payments measured, certified and released, and what advances, deductions or retention apply?
- Variations: Who can authorise changes, how are new items valued, and when do changes justify additional time or payment?
- Claim deadlines: What notices and supporting records are required, and do Syrian statutory deadlines apply alongside FIDIC procedures?
- Currency and adjustments: What is the contract currency, and how are exchange-rate changes and material price increases treated?
- Securities: Which performance bonds and guarantees are required, and what governs their validity, reduction and release?
- Delays: What triggers delay penalties, how are they capped, and when can the contractor obtain an extension of time?
- Insurance: Which construction insurance policies are required, who arranges and pays for them, and what exclusions apply?
- Disputes: Does the contract provide for DAAB proceedings, arbitration or court proceedings, and is the agreed procedure valid under applicable Syrian law?
- Decennial liability: Are the statutory responsibilities under Civil Code Articles 617–619 preserved without clauses attempting to exclude or restrict the applicable guarantee?
For each unresolved issue, obtain written clarification or an agreed amendment before signing. Particular Conditions should not transfer risks that the contractor has neither assessed nor accounted for in its price.
Read more: Infrastructure Contracting in Syria: Choosing the Right Contractor

How Qiwaa Advance supports EPC and formwork projects in Syria
For owners and contractors considering EPC or separately contracted works, the first task is defining who is responsible for design, procurement, installation and performance. These boundaries affect project pricing, variations and the risks each party must manage.
Through Qiwaa Contracting, we undertake EPC infrastructure works, including water networks, desalination and wastewater treatment facilities. Our partnerships with Amiantit and Variant Factory also support piping systems and concrete formwork and shoring solutions.
The appropriate arrangement depends on whether the project requires integrated design and construction, construction to an existing design, or a defined equipment supply package.
EPC vs separate design and construction
Both arrangements can be appropriate, but they distribute responsibility and project interfaces differently.
| Criterion | EPC with a single contractor | Separate design and construction |
|---|---|---|
| Design responsibility | Contractor assumes the design obligations defined in the contract | Employer typically appoints the designer; contractor’s design duties depend on its contract |
| Design and construction interfaces | Coordinated through the EPC contractor within the agreed scope | Employer or its consultant manages the designer–contractor interface |
| Programme | Design, procurement and construction may overlap where feasible | Construction generally follows sufficient design development and procurement |
| Design changes | Changes to the agreed Employer’s Requirements may affect price and time | Changes are assessed under the relevant design and construction agreements |
| Pricing and risk | A lump-sum EPC price may include a wider allocation of design and delivery risks | Construction pricing reflects the completed design, BOQ and allocated responsibilities |
Neither arrangement automatically guarantees faster delivery, a fixed final cost or fewer disputes.
For EPC projects, the Employer’s Requirements, available site information, performance criteria and Particular Conditions must clearly define the responsibilities transferred to the contractor.
Where design and construction are contracted separately, the owner must also address responsibility for design coordination, errors and changes affecting construction.
The relevant question is which party can manage each risk and whether that responsibility is clearly reflected in the contract and price.
Defining EPC and formwork supply scope before pricing
At Qiwaa Advance, we begin by reviewing the proposed work package and its technical requirements.
- For water networks and treatment facilities, this means establishing the boundaries between engineering, pipe and equipment supply, civil works, installation, testing and commissioning.
- For formwork and shoring packages, the scope may involve equipment supply and technical coordination rather than responsibility for the entire structure. The required systems depend on structural drawings, loading requirements, construction sequences and project geometry.
To discuss a project, we request:
- Employer’s Requirements: Project objectives, performance criteria and the current design stage.
- Drawings and BOQ: Available designs, specifications, quantities and equipment requirements.
- Responsibility boundaries: Which party handles design approval, procurement, installation, testing and interfaces with other contractors.
- Contract structure: Proposed EPC, design-build, construction-only or supply arrangement, including any relevant FIDIC conditions.
- Project details: Site location, schedule, contract currency and relevant delivery constraints.
These documents help us assess the proposed scope, identify technical and supply interfaces, and discuss suitable execution or equipment supply arrangements.
The resulting proposal should specify the responsibilities included, exclusions, technical assumptions and commercial conditions. Any final allocation of contractual risk must be agreed in the contract and reviewed by the parties’ legal and technical advisers.
Planning an EPC water infrastructure project or sourcing formwork systems in Syria? Contact Qiwaa Advance with your project requirements, drawings and proposed scope to discuss execution and supply options.

FAQs about FIDIC contracts in Syria
Are FIDIC contracts mandatory for Syrian government projects?
No. FIDIC forms are not automatically mandatory. Public contracts governed by Law No. 51 of 2004 must comply with the applicable Syrian legal framework, including Decree No. 450 of 2004 where relevant. FIDIC provisions may be incorporated where legally permitted.
What is the difference between the FIDIC Red Book and Yellow Book?
The main difference is design responsibility. Under the Red Book, the employer generally provides the design, and payment is typically based on remeasurement. Under the Yellow Book, the contractor designs to the Employer’s Requirements and is generally paid a lump sum. Particular Conditions may modify the standard allocation.
Can a construction contract in Syria exclude decennial liability?
No, where the statutory guarantee applies. Civil Code Article 617 covers qualifying structural collapse and defects threatening stability or safety during the ten-year period following handover. Article 619 expressly invalidates contractual clauses intended to exclude or limit that guarantee.
Can Syrian public contracts include arbitration?
Yes, subject to legal conditions. Article 66 of Law No. 51 of 2004 permits arbitration where provided for in the Particular Conditions and contract, under the prescribed administrative procedures. External contracts have separate provisions requiring the competent minister’s approval for a different arbitral body.
Sources
- Law No. 51 of 2004, Contracts Regulation (Arabic), Aleppo City Council, Legislative Data Bank, 9 December 2004
- Syria Amends Contracts Law, Allows Public Institutions More Leeway to Conduct Direct Procurement, The Syria Report, 26 May 2026
- New FIDIC Second Editions: revamped claims and dispute resolution provisions, CMS, 5 December 2017
- Introduction to FIDIC Contracts, James Perry, Islamabad, 28 August 2023
- FIDIC Yellow Book 2017: Quick Reference Guide, Clyde & Co, undated
- Conditions of Contract for EPC Turnkey Projects, 2nd Edition 2017, Reprinted 2022, FIDIC, 2022