Homs Reconstruction Projects and Tender Opportunities

On 30 July 2026, Japan and UN-Habitat signed an agreement to support the rehabilitation of Old Clock Square and solid waste management infrastructure in Homs. The Syrian Arab News Agency reported a value of $9.5 million, while the UN-Habitat announcement stated approximately $9.3 million (JPY 1.521 billion).

For contractors and suppliers following Homs Reconstruction, the key question is which announced projects have secured funding, who is responsible for implementation, and where construction or supply opportunities may emerge. This article examines confirmed agreements, major development projects, procurement channels, and potential work in infrastructure rehabilitation and rubble removal, distinguishing announced investments from contracts available for bidding.

Homs Reconstruction Damage Assessment

In May 2026, Syria’s Ministry of Local Administration and Environment, in cooperation with UN-Habitat, released a damage and needs assessment covering housing, education, and other public services across Homs Governorate. Based on data from the final quarter of 2025, the assessment provides a baseline for identifying reconstruction needs, although the reported damage does not establish which projects have received funding or entered procurement.

The findings are documented in the European Union Agency for Asylum’s assessment of infrastructure damage in Syria.

Extent of Damage in Homs

Indicator Reported figure English-language source
Residential units completely destroyed 5.2% EUAA, citing the May 2026 assessment
Residential units severely damaged 7% EUAA, citing the May 2026 assessment
Damaged schools 527, including 63 completely destroyed and 83 severely damaged EUAA, citing the May 2026 assessment
Estimated rubble in Homs More than 8 million m³ SANA, 30 September 2026

The housing and school figures cover Homs Governorate, while the rubble estimate comes from a separate report concerning Homs. These figures should not be treated as a single assessment with identical geographic and methodological coverage.

What these figures mean for contractors

  • Completely destroyed housing: Potential work includes demolition, debris clearance, site preparation, and replacement construction. The actual scope depends on structural assessments, ownership clearance, and approved redevelopment plans.
  • Severely damaged housing: Contractors need building-level assessments to determine whether structural strengthening, partial reconstruction, or demolition is required. The damage classification alone does not establish the appropriate intervention.
  • Damaged schools: Different damage levels indicate different rehabilitation requirements. Contractors should assess individual sites and technical specifications rather than assume that all schools can be covered by standardized work packages.
  • Rubble: Potential work includes clearance, hauling, sorting, and recycling. Contract scope will depend on site accessibility, designated processing facilities, environmental requirements, and procurement arrangements.

These figures indicate the scale of reconstruction needs and the types of work that may be required. They do not establish contract values, funded work packages, or tender schedules.

Where Homs Reconstruction Projects Are Located

Published project announcements identify several areas of activity, but they do not constitute a comprehensive, officially ranked reconstruction priority list for Homs Governorate. Contractors should distinguish the location of an announced development from evidence that its construction works are funded, approved, and available for bidding.

Four locations are particularly relevant to the projects discussed in this article:

  • Old Clock Square and surrounding markets: Urban regeneration and municipal service improvements under the Japan-funded UN-Habitat project.
  • Victory Boulevard corridor: A mixed-use development extending toward the Mimas area, including the wholesale market and dyehouses. The originally proposed redevelopment of the Qarabis neighborhood was subsequently excluded from the project following residents’ objections.
  • Karm al-Shami: An announced real estate development near the railway station, involving Saudi company Bayt al-Ibaa and the Syrian Oil Transport Company, as reported by Enab Baladi.
  • Homs municipal landfill: Rehabilitation of waste disposal infrastructure under the Japan-funded project.

Land ownership and planning approvals remain important project risks. Victory Boulevard illustrates why contractors should verify site readiness before committing resources.

In August 2025, Al-Omran announced that the Qarabis neighborhood redevelopment component would be cancelled following local opposition, while the wider boulevard project would continue. However, disputes concerning expropriated land remained unresolved in public reporting. In September 2026, residents protested the inclusion of disputed land in the boulevard development. Homs City Council maintained that the properties had legally passed into municipal ownership and were designated as a public park under an approved plan dating to the 1970s.

These developments are documented in North Press Agency’s report on the project cancellation and SANA’s English-language coverage of the September 2026 land protests.

For contractors and developers, the practical requirement is to verify the latest approved project boundaries, land-use designation, ownership and compensation status, and site handover conditions before pricing or committing to works. An announced development location does not, by itself, establish that the site is legally and operationally ready for construction.

Read more: Damascus Reconstruction 2026: Where to Invest and How to Start

Engineer measuring a crack in a concrete column during a building damage assessment

Status of Homs Reconstruction Projects

The main Homs reconstruction projects are at different stages of development. The Japan-funded initiative has confirmed financing and a published procurement notice for planning services, while Victory Boulevard and Karm al-Shami have been officially launched without publicly confirmed construction tender arrangements.

The table distinguishes each project’s announced scope from the information contractors and suppliers still need before pursuing work.

Project Responsible organization Confirmed status Published scope Information still needed
Japan-funded project Government of Japan and UN-Habitat Agreement signed on 30 July 2026; planning-services EOI issued in November 2026 Approximately $9.3 million; Old Clock Square, surrounding public spaces, and municipal solid waste management Budget allocation by component, construction packages, and award schedules
Victory Boulevard Al-Omran Holding, with HESCO Engineering as planning and design partner MoU signed in August 2025; commercial launch in August 2026 Initially 4,500 housing units; later approximately 2,500 mixed-use units Main works contractor, procurement arrangements, and clarification of revised project scope
Karm al-Shami (Homs Avenue) Saudi company Bayt al-Ibaa, in cooperation with the Syrian Oil Transport Company (IPC) Foundation stone laid on 29 August 2025 Approximately 270,000 m² of mixed-use development Confirmed budget, construction schedule, main contractor, and procurement arrangements

The project announcements establish different levels of commitment and readiness. A signed financing agreement, an investment launch, and a foundation-stone ceremony should not be treated as equivalent evidence that construction contracts are available.

Japan’s Clock Square and Landfill Project

On 30 July 2026, Japan and UN-Habitat announced an integrated urban reconstruction and solid waste management project in Homs.

According to the official UN-Habitat announcement, Japan is providing JPY 1.521 billion, approximately $9.3 million, for implementation from July 2026 to July 2028. The Syrian Arab News Agency reported the agreement’s value as $9.5 million.

The project has two principal components:

  • Old Clock Square: Rehabilitation of the square and surrounding public spaces, improvements to market organization, pedestrian safety, accessibility, and municipal management.
  • Municipal landfill: Rehabilitation of the final disposal site, improved waste collection and transport, and support for municipal waste management equipment. The announced approach includes the Fukuoka method, a semi-aerobic landfill system designed to improve waste decomposition and environmental performance.

The distinction between confirmed funding and available contracts is particularly important here.

On 13 November 2026, the United Nations Office at Nairobi (UNON), acting on behalf of UN-Habitat, published an Expression of Interest for an integrated urban study in Homs, reference EOIUNON24906, with a stated deadline of 23 November 2026.

The published scope includes site surveys, urban design, market organization, mobility assessments, and preparation of technical specifications, drawings, and bills of quantities.

This is a planning and design procurement opportunity, not a construction tender. Its publication confirms progress toward defining technical requirements but does not establish that civil works or equipment supply contracts have been awarded.

For contractors and suppliers, the next step is to monitor UNGM and subsequent UN-Habitat procurement announcements for approved work packages, technical specifications, and eligibility requirements. The allocation of the overall budget between project components has not been established in the reviewed public announcements.

Victory Boulevard Development

Victory Boulevard is one of Homs’ major announced mixed-use developments. However, its published scope changed between the initial investment agreement and commercial launch.

On 7 August 2025, Homs Governorate announced a memorandum of understanding with Al-Omran Real Estate Development and Investment Company. The project was described as providing approximately 4,500 housing units, alongside commercial, service, and tourism facilities.

At the commercial launch on 21 August 2026, Al-Omran Holding presented a development containing approximately 2,500 residential, commercial, administrative, and hotel units, across 500,000 m² of above-ground construction and 250,000 m² of underground parking.

These figures describe different mixes of units and cannot be compared as though both refer exclusively to housing. The published announcements do not explain the change sufficiently to establish whether it resulted from redesign, revised project boundaries, or another decision.

The August 2026 announcement identifies Al-Omran Holding as the implementing company and HESCO Engineering as a planning and design partner. It also describes three development stages, with implementation dependent on site handovers, particularly the existing wholesale market.

For contractors, the central question is not the total number of announced units but who will procure the structural, infrastructure, and building-services packages.

As of 23 November 2026, the reviewed public announcements do not identify a separate main works contractor or a defined tendering route for those packages. Contractors should therefore follow official developer announcements and confirm the contracting entity, site readiness, package boundaries, and procurement procedures before committing resources to bidding preparations.

Karm al-Shami Development

The Karm al-Shami development, also known as Homs Avenue, covers approximately 270,000 m² near the railway station in Homs.

According to Enab Baladi’s English-language report, the project is based on an agreement with Saudi company Bayt al-Ibaa, in cooperation with the Syrian Oil Transport Company (IPC).

The foundation stone was laid on 29 August 2025. The announced development includes residential, commercial, administrative, and service facilities. It was presented as a non-profit initiative intended to direct revenues toward supporting vulnerable and conflict-affected communities.

For contractors and material suppliers, the published development scope suggests potential future requirements for structural works, infrastructure networks, and building services. However, these remain potential categories of work, not confirmed procurement packages.

As of 23 November 2026, the reviewed sources do not establish a verified construction contract value, detailed execution schedule, separately appointed main contractor, or publicly announced procurement procedure.

Before treating the development as an actionable opportunity, contractors should obtain confirmation of the contracting entity, approved project specifications, construction schedule, and arrangements for supplier or subcontractor selection.

Also read: Aleppo Reconstruction Opportunities 2026: How to Identify the Best Investment Opportunities

Restoring a basalt and limestone facade in Homs with lime pointing

Homs Reconstruction Tenders

Published procurement notices provide a clearer route into water networks and rehabilitation work in Homs than major real estate announcements whose construction packages remain undefined. Contractors and suppliers should track opportunities through four channels:

  1. UNGM: Search UN procurement notices by location, agency, and work category. Complete the required supplier registration and check each notice’s eligibility and submission instructions. Registration alone does not guarantee tender invitations.
  2. Implementing agency websites: Monitor organizations such as GOAL, UNICEF, and UN-Habitat. Some agencies publish tenders through their own procurement systems, so UNGM should not be the only source.
  3. Governorate and ministry announcements: Follow public project announcements to identify responsible authorities, approved work scopes, and procurement arrangements. An announced project is not necessarily an invitation to bid.
  4. Property developers: Monitor developer announcements for main contractor appointments, subcontracting arrangements, and supplier registration procedures. These opportunities may follow private procurement routes rather than public tender platforms.

A current example is GOAL’s sewerage network rehabilitation tender, reference ITT-IDL-VFH-55767, published on 19 November 2026. It includes works in Eastern Buwayda, Homs Governorate, and Heish, Idlib Governorate.

The notice provides bills of quantities, technical specifications, drawings, and submission documents, with a stated deadline of 10 December 2026.

This gives contractors a defined scope to assess rather than an assumed future opportunity. Before preparing an offer, bidders should review the applicable lot, qualification requirements, specifications, site conditions, and contractual obligations. Material suppliers should use the published BOQ and technical specifications to establish which products are compliant, rather than assume that a particular pipe material or system will be accepted.

Lessons from the Closed UNICEF Tender

On 11 June 2026, UNICEF published a tender for the restoration of the sludge treatment facility at the Homs sewage treatment plant, identified as LRPS-2026-9204387 (Phase 2). The submission deadline was 11 July 2026, and the notice is now closed.

Although contractors can no longer bid, the published requirements provide useful evidence of how UNICEF structured this procurement.

The notice specified several conditions:

  • Bid submission: Technical and financial proposals had to be submitted separately through designated secure email procedures, with individual email size limits of 15 MB.
  • Currency and payment: International bidders were instructed to submit offers in USD or EUR. Local bidders could quote in USD or Syrian pounds, with payment in local currency according to the UN exchange rate specified in the notice.
  • Qualification and site access: Joint ventures involving international companies were encouraged, and the notice referred bidders to a scheduled site visit and the relevant qualification documents.

These details matter when assessing whether a company has the administrative, financial, and technical capacity to participate in similar tenders.

Contractors should retain the notice and available solicitation documents as references, then monitor subsequent UNICEF procurement announcements for related work. The Phase 2 designation identifies the published procurement package but does not confirm that another phase will be tendered.

The same distinction applies to other international projects in Homs. For example, UN-Habitat’s November 2026 Expression of Interest for the Old Clock Square urban study concerns planning and technical documentation, not an announced construction works contract.

Rubble Removal and Recycling in Homs

Rubble removal is an active component of Homs reconstruction, but the scale of debris should not be confused with the value of available contracts.

According to SANA’s English-language report, Homs had an estimated more than 8 million m³ of rubble. The report also describes a recycling initiative launched in March 2026 to process debris from the old bus station area and expand into other damaged neighborhoods.

The project involves Homs City Council and Etihad al-Omran, representing Turkish company Erkış, as documented in Syria Report’s English-language coverage.

A more recent development is the Subul rubble removal project, launched in November 2026 by Homs Governorate in coordination with the Ministry of Emergency and Disaster Management.

According to Enab Baladi’s English-language report, the project covers 75 sites, with approximately 750,000 m³ of material targeted for clearance, an estimated budget of up to $3 million, and a planned implementation period of 90 days.

The announced scope includes debris clearance, road reopening, removal of earthen barriers, and site grading. These are confirmed activities under an existing initiative, not evidence of additional contracts currently open for bidding.

For contractors evaluating rubble-related work, the main potential packages include:

  • Demolition and site clearance: Assessing unstable structures, defining demolition boundaries, and confirming property authorization before work begins.
  • Haulage: Estimating transport requirements using debris quantities, access conditions, haul distances, and approved disposal destinations.
  • Sorting and processing: Separating recoverable materials and identifying the equipment, facilities, and handling requirements specified by the project.
  • Recycling: Producing materials for approved applications, subject to testing, quality specifications, and acceptance requirements.

Explosive ordnance contamination is a critical constraint. The Subul project included site assessments by specialized teams before debris removal. UNDP’s Debris and Explosive Ordnance Guide also emphasizes risk-based assessment and appropriate specialist support for debris operations.

Contractors should establish who is responsible for site clearance authorization, explosive hazard assessment, debris ownership, disposal arrangements, and material acceptance before pricing such work.

Finally, the Japan-funded landfill rehabilitation project concerns municipal solid waste management. It should not be treated as a confirmed construction-rubble disposal or recycling contract without evidence that demolition debris falls within its approved scope.

Rows of repetitive residential concrete frames along a boulevard under construction

Homs Tender Checklist for Contractors

Before bidding on Homs reconstruction projects, contractors should assess more than the technical scope and estimated contract value. Funding, site access, contractual obligations, and procurement requirements can determine whether an opportunity is feasible and commercially viable.

Use the following checklist when reviewing tender documents, technical specifications, and contract conditions.

  1. Contracting authority: Identify the legal entity issuing the tender and signing the contract. Confirm whether procurement is managed by a government authority, international agency, developer, or appointed implementing partner.
  2. Funding availability: Establish whether financing has been approved for the specific work package, rather than relying on a broader project announcement. Check whether funding or donor approval conditions affect contract award.
  3. Land and site readiness: Verify site boundaries, legal access, land acquisition status, and outstanding ownership or compensation issues. The Qarabis dispute illustrates why an announced development does not guarantee site availability.
  4. Procurement and safety requirements: Review the contracting authority’s eligibility rules, evaluation criteria, environmental safeguards, and occupational health and safety obligations. Requirements may differ between public, donor-funded, and private contracts.
  5. Payment terms and currency: Confirm the quotation currency, payment currency, applicable exchange-rate provisions, advance payments, and payment milestones. Assess whether the terms expose the contractor to exchange-rate or cash-flow risks.
  6. Prequalification requirements: Check the required project references, financial statements, technical personnel, equipment capacity, and eligibility of joint ventures or subcontractors. Identify any mandatory thresholds before investing in bid preparation.
  7. Project phases and previous contracts: Determine whether the tender forms part of an existing project and whether earlier contracts affect the new scope, site access, or interface responsibilities. A previous phase does not guarantee future procurement.
  8. Bid validity: Confirm how long prices and contractual commitments must remain valid. Consider the implications for material pricing, supplier quotations, and guarantee validity.
  9. Submission deadlines: Review the final submission date, clarification deadline, mandatory site visits, and applicable time zone. Allow sufficient time to obtain technical quotations and prepare compliant documents.
  10. Language and submission format: Verify whether bids, supporting certificates, and qualification documents must be submitted in English or another specified language, and whether certified translations or separate technical and financial proposals are required.
  11. Financial guarantees: Determine whether bid security, a performance guarantee, or an advance-payment guarantee is required. Check the amount, acceptable issuing institutions, format, validity period, and release conditions.
  12. Technical specifications: Compare the BOQ, drawings, and material standards. For water networks, verify pipe materials, diameters, pressure classes, jointing requirements, testing procedures, and whether equivalent products are permitted.
  13. Material origin and compliance: Check country-of-origin restrictions, certificates of conformity, inspection requirements, and applicable import documentation. Confirm that proposed materials meet the contract’s approval requirements.
  14. Explosive ordnance risks: Establish who is responsible for assessing explosive remnants of war, arranging specialist clearance where required, and authorizing safe site access. The UNDP Debris and Explosive Ordnance Guide provides a technical reference for managing these risks.
  15. Measurement and payment certification: Review how completed quantities are measured, how variations are approved, and when interim payment certificates are issued. Check retention provisions and the documentation required for payment.
  16. Rubble management scope: For debris-related contracts, distinguish demolition, loading, transportation, sorting, recycling, and final disposal. Confirm who is responsible for approved disposal sites, hazardous materials, and testing recycled products.
  17. Execution schedule: Verify the contractual commencement date, site handover arrangements, construction milestones, and completion deadlines. Identify any dependencies on permits, design approvals, utility diversions, or other contractors.

These checks should support a bid-or-no-bid decision before substantial estimating resources are committed. If funding, site access, technical specifications, or payment conditions remain unclear, contractors should request written clarification through the designated procurement channel rather than price unresolved risks on assumptions.

For internationally funded tenders, the UNOPS Supplier Resource Centre and UNGM bidding guidance provide additional information on reviewing solicitation documents and preparing compliant submissions.

Plastering and electrical works in an apartment being rehabilitated in Homs

Qiwaa Advance Solutions for Homs Reconstruction

At Qiwaa Advance, we support contractors and developers with infrastructure materials and construction systems through our authorized manufacturing partners. While we do not claim involvement in any of the Homs reconstruction projects discussed in this article, our solutions may be relevant to future water infrastructure and residential construction contracts.

Our capabilities include:

  • Water and sewer networks: Through our authorized partnership with Saudi Arabia’s Amiantit Group, we support the supply of GRP pipe systems for suitable water and wastewater applications. We help contractors review pipe diameters, pressure and stiffness classes, jointing requirements, and technical specifications against the approved project design.
  • Residential and repetitive-floor construction: As an authorized partner of Variant Factory LLC, Qiwaa Advance provides access to tunnel formwork and other concrete formwork systems. We work with contractors to assess system suitability based on structural design, floor repetition, construction schedules, and site conditions.

The appropriate solution depends on the project rather than the scale of reconstruction announcements. GRP pipes must satisfy the network’s hydraulic, structural, and material specifications, while tunnel formwork requires compatible structural layouts and sufficient repetition to justify the system.

Tunnel vs Conventional Formwork

Tunnel formwork can offer execution advantages for repetitive residential buildings, but it is not necessarily the most economical choice for every project.

Criterion Tunnel formwork Conventional formwork
Floor repetition Suited to repeated layouts and consistent structural geometry Accommodates both repetitive and varied layouts
Design flexibility Requires early coordination of structural walls, slabs, and openings Allows greater flexibility when layouts or structural details vary
Site operations Requires planned lifting, formwork movement, and coordinated concrete casting Offers more flexibility in assembly and handling, depending on the system
Initial investment Typically requires a higher initial equipment commitment, offset by reuse when justified Generally involves lower initial investment, although repeated assembly increases labor requirements
Project suitability Most suitable where building design, repetition, and construction volume support efficient reuse Often more practical for smaller or irregular buildings

A peer-reviewed study on formwork selection identifies building geometry, repetition, labor, cost, and execution requirements as important factors in choosing between systems.

At Qiwaa Advance, we assess these factors against the contractor’s drawings and construction plan before recommending a suitable Variant system. Actual cycle times, equipment quantities, and cost implications must be evaluated for each project rather than assumed from general comparisons.

For further technical details, see our guide to tunnel formwork in Syria.

How We Support Contractors in Homs

Our approach begins with the project’s approved specifications and execution requirements, not a predetermined product recommendation.

For water and wastewater networks, contractors can provide their bill of quantities, pipeline drawings, required standards, pipe diameters, pressure and stiffness classes, and delivery schedule. Qiwaa Advance can then coordinate the relevant Amiantit product specifications and prepare a supply quotation based on the agreed requirements.

For residential construction, we review typical-floor drawings, structural layouts, planned casting sequences, crane availability, and project timelines. Working with Variant Factory, we can assess suitable formwork configurations and coordinate a project-specific technical and commercial proposal.

In both cases, our objective is to help contractors identify solutions that meet the project’s approved technical requirements while accounting for procurement and delivery constraints.

Planning a construction or infrastructure project in Homs? Send us your BOQ or structural drawings, relevant specifications, and required delivery date through WhatsApp. Our team at Qiwaa Advance will review your requirements and discuss suitable supply options for your project.

Wheel loader filling a tipper truck with stone rubble in a narrow street of old Homs

FAQs about Homs Reconstruction

Are there any open Homs reconstruction tenders?

Yes. As of 23 November 2026, GOAL has an open tender for sewerage network rehabilitation in Eastern Buwayda, Homs Governorate, under reference ITT-IDL-VFH-55767. The published submission deadline is 10 December 2026.

The notice includes technical specifications, drawings, and bills of quantities. Contractors should verify the current tender status and submission requirements directly with GOAL, as not all announced Homs reconstruction projects have reached the procurement stage.

How can contractors verify a project’s readiness?

Contractors should verify four conditions before allocating substantial bidding resources: confirmed funding for the relevant work package, approved technical documentation, legal site access, and an identified contracting authority with a defined procurement process.

For example, UN-Habitat’s Homs urban study concerns planning and design documentation, not a confirmed civil works tender. A funded project may still require design approvals, site handover, and separate procurement before construction begins.

Who handles construction contracts for Victory Boulevard?

Al-Omran Holding is identified as the company implementing Victory Boulevard, with HESCO Engineering involved in planning and design. However, the public announcements reviewed as of 23 November 2026 do not identify a separately appointed main construction contractor.

Contractors seeking work should confirm whether Al-Omran will procure construction packages directly or through appointed main contractors, and establish the relevant supplier or subcontractor selection procedures before submitting proposals.

Can suppliers bid directly on Homs reconstruction projects?

Yes, when a tender explicitly permits direct bids for the goods or services they provide and the supplier meets its eligibility requirements. However, material suppliers may need to work through a main contractor when procurement covers an integrated construction package.

For example, GOAL’s sewerage rehabilitation tender is a works procurement rather than a standalone pipe supply contract. Suppliers should review the tender’s subcontracting and material approval conditions before approaching bidders with technical specifications and quotations.

The UNGM procurement guidance explains how different solicitation procedures apply to goods, services, and construction works.

What documents should contractors prepare before bidding?

Contractors should maintain an updated prequalification file containing company registration documents, relevant project references, technical capabilities, financial records where required, and product compliance documentation.

For each tender, they must then prepare the specific submission forms, technical proposal, priced BOQ, execution schedule, and any required guarantees or certifications.

The UNGM registration requirements distinguish basic supplier registration from additional qualification levels. Contractors should check the requirements of each procurement notice rather than assume one document package satisfies every contracting authority.

Sources

  1. Japan Funds Urban Reconstruction Project in Homs: What Does It Include? (in Arabic), Al Jazeera Net, 31 July 2026
  2. Japan and UN-Habitat agreement for Homs city, SANA, 30 July 2026
  3. Press release on the Japan-funded project in Homs city, UN-Habitat, 30 July 2026
  4. Official Assessment Reveals Scale of Housing, Education and Bakery Damage in Homs (in Arabic), Syria TV, 2 May 2026
  5. Victory Boulevard Raises the Nightmare of the Homs Dream (in Arabic), Enab Baladi, 17 August 2025
  6. Al-Sharaa Launches Major Reconstruction Projects in Homs, Enab Baladi, 29 August 2025
  7. Report on Homs Boulevard and the Qarabis protest (in Arabic), SANA, 28 September 2026
  8. Report on rubble recycling in Syria (in Arabic), SANA, 29 September 2026
  9. Launch of the Victory Boulevard project in Homs (in Arabic), SANA, August 2026
  10. UNICEF notice LRPS-2026-9204387: Restoration of sludge treatment facility in Homs sewage treatment plant (phase 2), UNGM, 11 June 2026
شارك المقال:

مقالات أخرى

  • Rubble Removal in Syria: Who Tenders and How to Price It

    Rubble Removal in Syria: Who Tenders and How to Price It

  • Syria Reconstruction by Governorate: Where to Look for Work

    Syria Reconstruction by Governorate: Where to Look for Work

  • Latakia and Tartus Reconstruction Beyond Port Deals

    Latakia and Tartus Reconstruction Beyond Port Deals

  • Syria's 2026 budget: How Contractors Can Assess Payment Risk

    Syria’s 2026 budget: How Contractors Can Assess Payment Risk